Gear Mold Cavity:
The gear mold cavity is composed of all three gears on a single part. The cavity shows the side of the mold that will be exposed on the final yo-yo. There will be a runner going from the injection molding plastic point of entry to each of the gears (not pictured here).
Gear Mold Core:
The gear mold core is the back face of each of the gears. The mold core has three pegs (two of length 0.15" and one of length 0.1") that correspond to the gear placement on the gear mold cavity. The pegs are uniform in size throughout their length due to the small size of the gears. The gears will shrink around the center pegs and no tapper is needed. Around each peg is two holes for ejector pins. The ejector pin placement was aligned such that there is one pin on either side of the gear.
Dimensions:
The shrinkage for the gears was derived from measuring a small circular plastic part of similar dimensions as the gears. The circle had a 1.45 in diameter and the mold for it was roughly 2.5 % larger. The shrinkage of the gears was then determined using this formula ( Mold Increase %) = 2.5%* (Gear Diameter) / ( 1.45 in). For the big gear the mold was 1.6% larger, for the middle gear was 1.0 % larger, and the small gear was 0.8% larger. The inner gear holes are sized to have 0.248" diameter to create a press fit on the base which will have pegs of 0.25" diameter.
Process Plan:
Estimations of total machine time
Part
|
Machine
time on Mill (minutes)
|
Machine
time on Lathe (minutes)
|
Total
Machining Time (min)
|
Base Core
|
35
|
2.68
|
37.68
|
Base Cavity
|
0
|
1.47
|
1.47
|
Gears Core
|
33.17
|
0
|
33.17
|
Gears Cavity
|
31.47
|
0
|
31.47
|
Cover Die
|
1
|
2.35
|
3.35
|
Ring Core
|
0
|
4.97
|
4.97
|
Ring Cavity
|
1.27
|
2.12
|
3.39
|
TOTAL
|
101.91
|
13.59
|
115.5
|
Variable
time cost of making one Yoyo:
Part
|
Process
|
Rate determining step
|
RDS time (s)
|
Total cycle time estimate (s)
|
Base
|
Injection
molding
|
Cooling
of part
|
15
|
30
|
Gears
|
Injection
molding
|
Cooling
of part
|
10
|
25
|
Cover
|
Thermoforming
|
Heating
of plastic
|
5
|
20
|
Ring
|
Injection
molding
|
Cooling
of part
|
5
|
15
|
TOTAL
|
90
|
As seen from the values above, the
greater time cost involves the machining of the molds. Having a total of 7 mold
components requires a total machining time of almost 2 hrs. However, the
process has been optimized to keep this value to a minimum. The three gears are
being made via the same mold, which decreases both machining time and injection
molding time by almost a factor of three. Additionally, the thickness of the
case and ring have been minimized in order to decrease the time taken for the
cooling of these parts, which is the rate limiting step for injection molding.
Thus, none of the components have excessive thicknesses. By using both,
thermoforming and injection molding, for different components, we will be able
to fabricate them simultaneously, improving the total process time of producing
50 Yoyos.
Our estimated cycle times for the
different components are based on our knowledge of the rate determining step,
the critical dimensions of the parts, and previous time estimates discussed in
lectures. Typical cycle times from lecture were taken and scaled down to fit
our parts. It is important to note the amount of time it will take to start up
machines for both the making of the molds, and the actual injection molding
process is relatively significant compared to other parts of the process, since
it is not automated. The cycle time estimate considers this component. The
addition of all these times sets an estimate of producing a hundred yoyo sides
of about 4.5 hours. (This does not consider the need for multiple trial runs, or
mold modification.) The assembly time is estimated to be 1 minute per Yoyo.
This may seem as an overestimate, but we are accounting for possible fitting
problems, coordination of different teams, possibility of errors, and the time
it takes to familiarize oneself with the assembly process. (Assembly time can
vary depending on the people taking part in the process.) Therefore, total
assembly time for all Yoyos is estimated to be 50min.
Manufactured Molds:
The mold has three posts on the core side which the plastic will contract and stick to after cooling. The ejector pins will push out the gears from either side of the post. The cavity side has the gear shapes and includes a runner for the plastic to flow through. These are the second iterations of the gear mold machining. The initial test resulted in parts that did not line up due to an error in mirroring. However, each side of this mold now fits together very well and is ready for an initial injection molding test.